Developing the Infrastructure



Summer 2002: A half-mile of water and electrical lines were buried in trenches. Also a half-mile gravel road complete with fire hydrants was constructed.

Fall 2003: We worked alongside a professional crew to install the 30,000-gallon water tank at hilltop. Water from the new tank serves for domestic needs and fire protection.